GROUP C Altiris/AV Project progress   As of 09-13  
Tom Kascak        
Giovanni Bedoya        
Alejandro Torres        
REGION C Status of completion PCs estimated left   Status of completion PCs estimated left
Jewish Studies - 96 Wentworth done 0 6 Glebe done 0
Randolph done 0 14 Glebe done 0
Simmons Center (Art) n/a 1 to reformat 0 26 Coming na friedman doesn't want has norton 2003 1
Towell Library done 0 8 Bull ( Avery Research Center) done 0
Sottile House done 0 16 Glebe done 0
181Calhoun St. (wellness) done 0 11 Glebe done 0
26 Glebe St. done 0 45 Coming done 0
20 Glebe St. done 0 55 Coming done 0
5 College done 0 59 Coming done 0
67 George St. done 0 Porter Lodge completed now that wireless is installed. 0
Stern Center done 0 88 Wentworth done 0
40 Coming St. done 0 22 Glebe done 0
114 Wentworth done 0 14 Coming done 0
44 St. Philip done 0 18 Bull - Blacklock House done 0
       

Total estimated PCs to load Altiris and NAV:  0 

Total estimated PCs with Altiris and NAV: 307